An update on the construction progress of LAVIQ Sukhumvit 57 for Q1/2018. The project was undergoing floor and structural column reinforcement, structural concrete pouring, elevator wall works, 5th-floor works, and stair works, with actual progress at 8.14%, which was 0.70% ahead of the planned schedule.
REAL ASSET executives, together with Nara Consultant, Syntec, and Melcon, inspected construction quality and monitored the progress of LAVIQ Sukhumvit 57, a luxury condominium project in the Sukhumvit area. According to the source content, the project was in the structural stage of pouring the 3rd-floor slab.
------------------------------------------